Skip to content

How to Build a SOC 2 Audit Dashboard in Excel Step by Step

Build a SOC 2 audit dashboard in Excel that tracks trust services criteria, control status, evidence and findings, with a sample layout, tested formulas and a worked example.

  • Shahidul Shubo
  • 19 min read
How to Build a SOC 2 Audit Dashboard in Excel Step by Step

Three weeks before fieldwork, a US client asks one question: "Are you on track for the report?" If the answer means opening five spreadsheets and asking four people, you have records but no dashboard.

A SOC 2 audit dashboard in Excel can answer that question on one page. Most spreadsheets fail at it because they count documents, while a Type 2 auditor tests whether controls operated for the whole period. This guide builds one that checks the second thing, with a sample layout and formulas you can copy. Every formula was entered in a blank workbook and checked against planted errors in desktop Excel 2013 on 25 November 2026. No macros are needed.

Quick answer: how do you build a SOC 2 audit dashboard in Excel?

Create seven linked sheets (Settings, Criteria, Controls, Evidence, Tests, Findings, Dashboard) plus a small lookup list. Give every control one ID, map it to Trust Services Criteria references, and log evidence, tests and findings against that ID. Let formulas set the control status, then summarise coverage, test progress, evidence and open findings on the dashboard.

SOC 2 audit dashboard Excel layout showing Settings and Criteria feeding the Controls sheet, with Evidence, Tests and Findings linked by control ID and summarised on the Dashboard
The layout used in this guide. One control ID links every sheet.

What should a SOC 2 dashboard track?

Track six things: criteria coverage, control status, evidence, operating tests, findings and time left in the period. Each one answers a question somebody will ask you.

Area

Question it answers

Measure to show

Trust services criteria

Does every in-scope criterion have at least one control?

Criteria with no mapped control

Control status

Is each control designed, in place and working?

Effective controls as a share of those in scope

Evidence collection

Has the evidence arrived, and does it cover the right dates?

Accepted, overdue, rejected, and period gaps

Operating tests

Has the control been tested across the period?

Tests completed against tests due, capped

Open findings

What could end up in the report?

Open and overdue findings, plus deviations already fixed

Time

How long is left to collect clean operation?

Days to period end and share of period elapsed

Trust services categories and criteria counts

SOC 2 uses five categories. The numbered items inside them, such as CC6.1, are the criteria. Reports are currently prepared against the AICPA's 2017 Trust Services Criteria with revised points of focus (2022).

Category

References

Criteria

In scope?

Security (common criteria)

CC1.1 to CC9.2

33

Always

Availability

A1.1 to A1.3

3

If chosen

Processing integrity

PI1.1 to PI1.5

5

If chosen

Confidentiality

C1.1 to C1.2

2

If chosen

Privacy

P1.1 to P8.1

18

If chosen

Total

61

Counts as listed by Secureframe; the total of 61 is also given by the CPA firm Linford & Company. Points of focus support each criterion. They are not a checklist of mandatory controls.

Type 1 or Type 2 changes the dashboard

A Type 1 report looks at controls as of one date. A Type 2 report looks at how they operated over a period, typically 3 to 12 months. For Type 1 you can skip the Tests sheet at first. For Type 2 it is the most important sheet in the file.

One wording point, because buyers notice it: SOC 2 is an attestation report issued by a CPA firm. There is no "SOC 2 certificate", and no dashboard can produce the auditor's opinion.

Before you open Excel

Agree these with your service auditor or compliance lead first. Changing them later means rebuilding formulas.

  • System boundary: which product, locations, teams and vendors are covered.

  • Categories: Security, plus whatever your contracts ask for.

  • Report type and period: start date, end date and target issue date.

  • Control list: your own controls, in your own words, each with a named owner.

  • Test frequency: how often you will check each control internally.

If you outsource development or support, list those vendors now. In our guide to how internal audit works I wrote that the gap I find most often is vendor access that is never removed after the contract ends. That gap lands directly on the access criteria, so give vendor offboarding its own control row.

SOC 2 dashboard template: the sample Excel layout

Make each data range an Excel table (Ctrl+T) and rename it on the Table Design tab. Formulas then read like sentences, and new rows are included automatically.

Sheet (table name)

You type

Formulas fill

Settings

Period start, period end, optional as-of date

As-of date, days in period, share elapsed

Lists (tFreq)

Frequency, Per year

None

Criteria (tCriteria)

Ref, Category, In scope

Mapped, Effective, Ineffective, State

Controls (tControls)

Control ID, Control, Criteria, Owner, Frequency, Risk, Implementation

Key, Planned, Due, Done, Counted, Slot gap, Deviations, Open findings, High open, Evidence issues, Rows to fix, Status

Evidence (tEvidence)

Evidence ID, Control ID, Type, Covers from, Covers to, Due, Received, Review, Link

Status, Period check, Issue

Tests (tTests)

Test ID, Control ID, Operated on, Method, Population, Sample, Exceptions

Result, In period, Slot, Check

Findings (tFindings)

Finding ID, Control ID, Test ID, Identified, Severity, Likelihood, Impact, Owner, Target, Closed

Status, Report outlook

Dashboard

Nothing

Everything

Here is how a few Controls rows look once filled in. All records are illustrative.

Control ID

Control

Criteria

Owner

Frequency

Risk

Implementation

C-01

User access review

CC6.2; CC6.3

IT Manager

Quarterly

High

Implemented

C-02

Leaver access removal

CC6.2

HR Manager

Event-driven

High

Implemented

C-03

Change approval before release

CC8.1

Engineering Lead

Monthly

High

Implemented

C-05

Backup restore test

A1.3

IT Manager

Semi-annual

Medium

Partial

C-06

Critical vendor review

CC9.2

Risk Manager

Annual

Medium

Not implemented

Step 1: Set the audit period once

Put the dates on Settings and name the cells, so every sheet reads the same period. Select a cell and type its name in the Name Box.

Cell

Name

Value or formula

B3

PeriodStart

1 Jan 2026 (example)

B4

PeriodEnd

31 Dec 2026 (example)

B5

(none)

Optional override date, normally blank

B6

AsOf

=IF(B5="",TODAY(),B5)

B7

PeriodDays

=B4-B3+1

B8

Elapsed

=MEDIAN(0,1,(B6-B3+1)/B7)

The override matters more than it looks. Without it, the figures in last month's board pack change every time somebody opens the file. Enter a date, save a copy, and that version stays fixed.

On Lists, create tFreq: Annual 1, Semi-annual 2, Quarterly 4, Monthly 12, Event-driven 2. These are planning assumptions for internal checks. Your auditor sets their own sample sizes.

Step 2: Map controls to trust services criteria

List each in-scope reference on the Criteria sheet, one per row. On Controls, type the references in one cell separated by semicolons, because one control often supports several criteria. Then add a Key column:

Key:         =";"&SUBSTITUTE([@Criteria]," ","")&";"

And on Criteria:

Mapped:      =COUNTIFS(tControls[Key],"*;"&[@Ref]&";*",tControls[Status],"<>Not applicable")
Effective:   =COUNTIFS(tControls[Key],"*;"&[@Ref]&";*",tControls[Status],"Effective")
Ineffective: =COUNTIFS(tControls[Key],"*;"&[@Ref]&";*",tControls[Status],"Ineffective")
State:       =IF([@[In scope]]="No","Out of scope",IF([@Mapped]=0,"NO CONTROL",
             IF([@Ineffective]>0,"At risk",IF([@Effective]=[@Mapped],"Ready","In progress"))))

Why the semicolons? "C1.1" (confidentiality) is hidden inside "CC1.1" (control environment). A plain wildcard search for *C1.1* counts your code of conduct as a confidentiality control and hides a real gap. In our test file the plain search returned 1 and the delimited search returned 0, which is correct.

Excel's COUNTIFS documentation covers wildcard behaviour if you want to adapt this.

Step 3: Build the control register

Add drop-down lists for Owner, Frequency, Risk and Implementation. For Frequency, the list source is =INDIRECT("tFreq[Frequency]"). Use four Implementation values only: Implemented, Partial, Not implemented, Not applicable.

These columns calculate the testing position:

Planned:  =IF([@Implementation]="Not applicable",0,MAX(1,ROUND(INDEX(tFreq[Per year],
          MATCH([@Frequency],tFreq[Frequency],0))*PeriodDays/365,0)))
Due:      =ROUND([@Planned]*Elapsed,0)
Done:     =COUNTIFS(tTests[Control ID],[@[Control ID]],tTests[In period],1)
Counted:  =MIN([@Done],[@Due])

Counted stops one over-tested control from covering for an untested one. In our test file, coverage was 58% without the cap and 47% with it. The lower number is the honest one.

Use roles rather than people's names for owners, so the register survives staff changes. If ownership itself is unclear, sort that out first; our article on the layers of governance explains who usually decides what.

Step 4: Track evidence by the dates it covers

Most trackers ask "received: yes or no?" That misses the failure that hurts in a Type 2: evidence that arrived on time but covers only part of the period. Add Covers from and Covers to, and set Type to Population (a full list, such as all changes) or Sample (one item, such as a ticket).

Status:       =IF([@Received]="",IF([@Due]<AsOf,"Overdue","Pending"),
              IF([@Review]="","Under review",[@Review]))
Period check: =IF([@Received]="","",IF([@Type]="Population",
              IF(AND([@[Covers from]]<=PeriodStart,[@[Covers to]]>=MIN(PeriodEnd,AsOf)),"OK","Gap"),
              IF(AND([@[Covers from]]>=PeriodStart,[@[Covers to]]<=PeriodEnd),"OK","Gap")))
Issue:        =--OR([@Status]="Overdue",[@Status]="Rejected",[@[Period check]]="Gap")

In the Review column, allow only Accepted and Rejected. A change export starting in April will now show "Gap" even though somebody marked it Accepted. Expect "Gap" on an old population until it is refreshed up to the as-of date; that is the reminder working.

Completeness needs a human. Linford's note on information produced by the entity explains what service auditors look for: that all data is captured, the report logic is right and the parameters were applied correctly. So record the system name, query or filter, run date and row count with each population. In database audits I ask for query results or exports that show the instance name and date, and the same habit works here.

Store links in the Link column, not the files themselves. A workbook full of screenshots and user lists becomes a sensitive asset with weak access control.

Step 5: Log operating tests properly

One row per test. The column to get right is Operated on: the date the control worked, not the date you tested it. Testing often continues after the period closes. If you count by test date, valid in-period samples drop out, and old samples tested during the period slip in.

Result:    =IF([@Exceptions]="","",IF([@Exceptions]=0,"Pass","Deviation"))
In period: =IF([@[Operated on]]="","",--AND([@[Operated on]]>=PeriodStart,[@[Operated on]]<=PeriodEnd))
Slot:      =IF([@[In period]]=1,INT(([@[Operated on]]-PeriodStart)/(PeriodDays/4))+1,"")
Check:     =IF([@Sample]>[@Population],"Sample > population",
           IF([@Exceptions]>[@Sample],"Exceptions > sample",
           IF(AND([@Method]="Inquiry",[@Result]="Pass"),"Inquiry only",
           IF(AND([@Result]="Deviation",COUNTIFS(tFindings[Test ID],[@[Test ID]])=0),"Log finding","OK"))))

If one test uses several samples from different dates, give each date its own row. Enter 0 in Exceptions when there are none, because a blank means the test is not finished. The result is calculated, so nobody can type "Pass" beside two exceptions.

The "Inquiry only" flag is deliberate. A partner at Linford, writing on audit sampling in SOC examinations, says that "a walkthrough or inquiry only would not be sufficient to test all controls". Asking the owner is a start. Add inspection, observation or reperformance.

The spread test most spreadsheets miss

Four quarterly reviews all done in December still make "4 of 4". To catch that, split the period into four equal slots and check that each finished slot contains at least one test. Add this to Controls:

Slot gap: =IF([@Planned]>=4,SUMPRODUCT((COUNTIFS(tTests[Control ID],[@[Control ID]],
          tTests[Slot],{1,2,3,4})=0)*({1,2,3,4}<=INT(4*Elapsed+0.01))),0)

The slots are equal quarters of your period, not calendar quarters, so a six-month window works too. Only controls with four or more planned tests are checked. The 0.01 is a small rounding allowance at slot boundaries.

Step 6: Record findings and keep fixed ones visible

In a Type 2 engagement, closing a finding does not erase the deviation. The CPA firm Schellman explains that findings still appear in a Type 2 report whether or not they were remediated, and that corrective action can be described alongside them. A dashboard where red turns green on closure gives management a false picture.

Status:         =IF([@Closed]<>"","Closed",IF([@Target]<AsOf,"Overdue","Open"))
Report outlook: =IF(COUNTIFS(tTests[Test ID],[@[Test ID]],tTests[In period],1,
                tTests[Result],"Deviation")=0,"Internal finding",
                IF([@Closed]<>"","Deviation, remediated","Deviation, still open"))

Report outlook is a management indicator for your own planning. The service auditor runs separate tests and decides what is reported. A deviation also doesn't automatically mean a qualified opinion: the auditor weighs its nature, cause and extent.

For a 5×5 risk heatmap, put likelihood 1 to 5 down column A, impact 1 to 5 across row 4, and fill:

=COUNTIFS(tFindings[Likelihood],$A5,tFindings[Impact],B$4,tFindings[Status],"<>Closed")

Step 7: Let one rule decide control status

Control owners should not choose their own colour. Add the supporting columns, then the Status rule, which stops at the first condition that applies:

Deviations:      =COUNTIFS(tTests[Control ID],[@[Control ID]],tTests[In period],1,tTests[Result],"Deviation")
Open findings:   =COUNTIFS(tFindings[Control ID],[@[Control ID]],tFindings[Status],"<>Closed")
High open:       =SUM(COUNTIFS(tFindings[Control ID],[@[Control ID]],tFindings[Status],"<>Closed",
                 tFindings[Severity],{"High","Critical"}))
Evidence issues: =SUMIFS(tEvidence[Issue],tEvidence[Control ID],[@[Control ID]])
Rows to fix:     =COUNTIFS(tTests[Control ID],[@[Control ID]],tTests[Check],"<>OK")

Status: =IF([@Implementation]="Not applicable","Not applicable",
        IF(OR([@Implementation]="Not implemented",[@[High open]]>0),"Ineffective",
        IF(AND([@Done]=0,[@Due]>0),"Not tested",
        IF(OR([@Implementation]="Partial",[@Done]<[@Due],[@[Slot gap]]>0,[@[Open findings]]>0,
        [@[Evidence issues]]>0,[@[Rows to fix]]>0),"Needs attention","Effective"))))

"Rows to fix" earned its place during testing. In the first version, a control with a deviation and no logged finding still came out as Effective. The extra column closes that hole.

Step 8: Build the dashboard page

Keep it to one screen: period and days left at the top, six to eight KPI tiles, then criteria coverage, the control queue and overdue findings.

Controls in scope:         =COUNTIFS(tControls[Status],"<>Not applicable")
Effective controls:        =IFERROR(COUNTIFS(tControls[Status],"Effective")/
                           COUNTIFS(tControls[Status],"<>Not applicable"),0)
Criteria with no control:  =COUNTIFS(tCriteria[State],"NO CONTROL")
Test coverage:             =SUM(tControls[Counted])/SUM(tControls[Due])
Evidence accepted:         =COUNTIFS(tEvidence[Status],"Accepted",tEvidence[Due],"<="&AsOf)/
                           COUNTIFS(tEvidence[Due],"<="&AsOf)
Overdue findings:          =COUNTIFS(tFindings[Status],"Overdue")
Deviations in period:      =COUNTIFS(tFindings[Report outlook],"Deviation*")
Days left:                 =PeriodEnd-AsOf
Test rows to fix:          =ROWS(tTests[Check])-COUNTIFS(tTests[Check],"OK")
Unknown control IDs:       =SUMPRODUCT(--(COUNTIFS(tControls[Control ID],tTests[Control ID])=0))

Wrap the two ratio formulas in IFERROR(…,0) if nothing is due yet. To list every control that needs work without macros or filters, put this in D20 and fill down:

=IFERROR(INDEX(tControls[Control ID],AGGREGATE(15,6,(ROW(tControls[Status])-ROW(tControls[[#Headers],[Status]]))
/ISNUMBER(MATCH(tControls[Status],{"Ineffective","Not tested","Needs attention"},0)),ROWS(D$20:D20))),"")

Add a readiness verdict with gates

An average can hide the one thing that stops the report, so set the verdict with gates. Replace the cell names below with your own KPI cells:

=IF(OR(NoControl>0,SUM(tControls[High open])>0,
 COUNTIFS(tControls[Status],"Ineffective",tControls[Risk],"High")>0),"NOT READY",
 IF(AND(EffectivePct>=0.9,TestCoverage>=0.95,RowsToFix=0),"READY","IN PROGRESS"))

The 90% and 95% levels are our suggestion. There is no AICPA pass mark for a readiness score.

Step 9: Format, protect and test it

Use conditional formatting with a formula rule, for example =$S2="Ineffective" where column S holds Status. Keep the words as well as the colours, so the page still works in black and white and for colour-blind readers. Lock formula columns, keep one master copy with version history, and restrict who can open it.

Then break it on purpose. Plant these records and check that your workbook reacts the same way. These are the results from our own test file, with the as-of date set to 30 September 2026:

Planted record

Correct result

Monthly control with one in-period test, on 1 July

Due 9, Done 1, Slot gap 2, Needs attention

Sample that operated on 20 December 2025

In period 0, not counted

Quarterly control tested on 2 July, 2 August and 2 September

3 of 3 done, but Slot gap 1, Needs attention

2 exceptions entered for a sample of 1

"Exceptions > sample", control not Effective

Inquiry as the only method, result Pass

"Inquiry only", control not Effective

Population covering April to September

Period check: Gap

Deviation whose finding is closed

Control Effective, outlook "Deviation, remediated"

Only CC1.1 mapped, C1.1 in scope

C1.1 shows NO CONTROL

How to read a SOC 2 readiness score: a worked example

A single score can look comfortable while most controls are not ready. The screenshot shows the GRCkits SOC 2 Type 2 dashboard with its sample data, 36 days before the end of a 12-month period.

SOC 2 audit dashboard in Excel with sample data showing a readiness score of 77, rating At Risk, 93 percent operating effectiveness, 23 percent of controls effective and seven open exceptions
GRCkits SOC 2 Type 2 workbook. Company, auditor and results are sample data.

Component

Weight

Score

Points

Control implementation

30%

82%

24.6

Testing coverage

25%

73%

18.2

Operating effectiveness (clean tests)

25%

93%

23.3

Evidence completeness

10%

76%

7.6

Exception remediation

10%

36%

3.6

Readiness score

77.3

The score is 77. Yet only 16 of 69 applicable controls (23%) are Effective, 35 are behind on testing, and all seven open exceptions are overdue. Why the distance? The 93% describes tests that were performed. It says nothing about the tests nobody has done. And each weak control loses only part of its points in an average.

The workbook handles this by showing a separate opinion-risk flag, which reads HIGH beside the 77. Do the same in yours: never present the score alone.

Monitor SOC 2 readiness alongside ISO 27001

Many software and IT outsourcing firms carry both: ISO 27001 for European buyers and SOC 2 for American ones. Running two registers doubles the updating and lets the answers drift apart. Keep one control list and add a SOC 2 column.

The GRCkits Cybersecurity Assessment Dashboard is a practical base for the readiness stage. It is macro-free, holds 131 controls in 17 domains mapped to ISO/IEC 27001:2022 and NIST CSF 2.0, turns every non-compliant or partially compliant control into a finding, and plots the results on a 5×5 heatmap. It has no SOC 2 column, but one can be added without touching its protected sheets:

  1. On the Assessment sheet, use the first empty column (AM) for SOC 2 criteria and enter references such as CC6.2; CC6.3.

  2. In AN6, enter =IF($AM6="","",";"&SUBSTITUTE($AM6," ","")&";") and fill down to row 305.

  3. Add a sheet called TSC Coverage and list the criteria in column A from row 2.

  4. Enter the four formulas below in row 2 and fill down.

B2 Mapped:    =COUNTIFS(Assessment!$AN$6:$AN$305,"*;"&$A2&";*")
C2 Compliant: =COUNTIFS(Assessment!$AN$6:$AN$305,"*;"&$A2&";*",Assessment!$K$6:$K$305,"Compliant")
D2 Findings:  =COUNTIFS(Assessment!$AN$6:$AN$305,"*;"&$A2&";*",Assessment!$AA$6:$AA$305,"Yes")
E2 State:     =IF($B2=0,"No control mapped",IF($D2>0,$D2&" open finding(s)",IF($C2=$B2,"Ready","Assess")))

On the sample file, CC6.2 mapped to three access controls returned one compliant, two findings and the state "2 open finding(s)". The findings register and heatmap keep working as before. An indicative starting map using the workbook's own control IDs:

Workbook control

ISO/IEC 27001:2022

SOC 2 criteria (indicative)

GOV-01 Information security policy

A.5.1

CC5.3

RSK-03 Periodic risk assessment

Clause 8.2

CC3.2

IAM-03 Timely de-provisioning

A.5.18

CC6.2, CC6.3

IAM-04 User access reviews

A.5.18

CC6.2, CC6.3

NET-04 Perimeter protection

A.8.20

CC6.6

END-01 Endpoint protection coverage

A.8.7

CC6.8

VUL-01 Vulnerability scanning

A.8.8

CC7.1

LOG-04 24×7 security monitoring

A.8.16

CC7.2

IRM-01 Incident response plan

A.5.24

CC7.4

CFG-03 Change management

A.8.32

CC8.1

TPR-04 Ongoing supplier monitoring

A.5.22

CC9.2

BCR-05 Restore testing

A.8.13

A1.3

Limits of this mapping. Overlap is partial. An ISO 27001 certificate does not satisfy SOC 2, and a compliant row is not a period of operating evidence. The AICPA publishes its own mapping to ISO 27001 for members, but the page is dated 2018 with March 2020 updates, so it predates the 2022 edition's Annex A numbering. Confirm your map with the service auditor. For Type 2 testing, use the layout in this guide or the dedicated SOC 2 workbook, whose 72 controls are mapped at category level; add the Criteria column from Step 2 if you need criterion-level coverage. That workbook uses MAXIFS, so it needs Excel 2019 or later, or Microsoft 365.

If you already maintain an ISO 27001 Statement of Applicability, its owner and evidence columns can feed the same control list.

Prepare for the proposed 2027 criteria

Do not hard-wire criterion numbers into control IDs. In November 2026 the AICPA posted exposure drafts of proposed 2027 Trust Services Criteria and Description Criteria. They are not final. According to A-LIGN and Secureframe, comments close on 15 January 2027 and, if finalised, the criteria would apply to engagements beginning on or after 31 December 2027, with early implementation permitted.

For a dashboard, the risk is reused numbers. Security would go from 33 criteria in nine series to 20 in eight, and access moves from CC6 to CC5 while CC6 becomes system operations. Mix the two sets in one column and "CC6.1" means two different things. So:

  • Keep neutral control IDs such as C-01.

  • Rename the column Criteria (2017), and add Criteria (2027) only when a final text exists.

  • Record on Settings which version the current engagement uses.

Common SOC 2 dashboard mistakes

Mistake

Why it hurts

Do this instead

Counting evidence files as readiness

Files can cover the wrong dates

Check the period each item covers

Marking a control Effective after one sample

Type 2 is about the whole period

Use the Due and Slot gap columns

Showing only the latest test result

An earlier deviation disappears

Count every deviation in the period

Mapping to categories only

A criterion can have no control at all

Map to criterion references

Undated reviews

The review date is the evidence gap I described as most frequent in software vs spreadsheets

Make the date a required field

Macro-driven workbooks

Office on Windows blocks macros in files from the internet by default

Use formulas only

When Excel is not enough

Excel suits one system, one period and a small team that updates it on a fixed day each week. Move to a compliance platform when evidence must be pulled from many cloud systems every day, when several people edit at once, or when you need a tamper-evident change log. Excel gives you none of those by default. A useful warning sign: if chasing updates takes longer than fixing controls, the tool has become the problem.

Frequently asked questions

Can I use Excel for SOC 2 compliance?

Yes, for planning, tracking and readiness. No tool is mandated for running your programme. The CPA firm still performs its own testing, and the workbook does not replace source evidence from your systems.

How many controls should a SOC 2 dashboard have?

There is no required number. You need enough controls to meet every in-scope criterion. The sample workbook shown here holds 72. Count uncovered criteria, because a long control list can still leave a gap.

What is the difference between control status and evidence status?

Evidence status says whether a document arrived and was accepted. Control status says whether the control is in place and operating. Evidence can be 100% accepted while the control fails, because the evidence shows the failure.

How often should the dashboard be updated?

Weekly works for most teams during the observation period, and daily during fieldwork. Save a dated copy each month using the as-of override, so you can show the trend.

Does a remediated exception still appear in a SOC 2 Type 2 report?

Generally yes, if the deviation happened inside the period and the auditor's testing identifies it. Remediation and management's response can be described too. Ask your auditor how they will present it.

Can one dashboard cover SOC 2 and ISO 27001?

Yes, with one control list and separate mapping columns. Keep the results separate: ISO 27001 leads to certification by a certification body, and SOC 2 leads to a CPA's attestation report.

Key takeaways

  • Map controls to criteria references with delimiters, so C1.1 never matches CC1.1.

  • Count tests by the date the control operated, cap the count, and check the spread.

  • Check which dates the evidence covers as well as whether it arrived.

  • Keep remediated deviations visible until the report is issued.

  • Use gates for the verdict, and never show a readiness score by itself.

Your next step: build the Criteria sheet today and look for rows that say NO CONTROL. That one list usually decides the next month's work. If you would rather start from a working file that also covers ISO 27001, the 131-control assessment dashboard can be adapted with the steps above. For an independent view before fieldwork, see our IS audit service.

This is general guidance, not legal advice or an attestation opinion. GRCkits sells the two workbooks named here. The AICPA does not endorse them. Check all criteria against the AICPA text and agree scope, sampling and reporting with your service auditor.

Share LinkedIn X Facebook Email
Shahidul Shubo

Written by

Shahidul Shubo

Cybersecurity GRC Consultant

Shahidul Shubo is a Cybersecurity GRC Consultant with 10+ years of experience in information security governance, risk management, regulatory compliance and IT audit, and has audited more than 120 organisations. He is CISA and CISM certified, an ISO/IEC 27001 Lead Auditor and Lead Implementer, and a Lead Auditor for ISO/IEC 27701, ISO/IEC 42001, ISO 22301 and ISO 9001. His technical credentials include AWS Solutions Architect, AWS Security Specialty, Red Hat RHCA and RHCE, Fortinet NSE and CCEP. He works hands-on with ISO 27001, NIST CSF and NCA ECC, and builds the practical templates and assessment tools published on GRCkits.

Connect on LinkedIn

Need hands-on help?

IS Audit

Independent information systems audits that strengthen IT governance and demonstrate compliance.

Request an audit

Keep reading

Related articles

Need help? Chat with us